Tim,

What you are looking for is not currently the case, the external shutdown
behavior is different from the one initiated by the input operator. I
created a JIRA to fix this a while ago:

https://issues.apache.org/jira/browse/APEXCORE-294

Thomas

On Tue, Jan 26, 2016 at 2:54 PM, Amol Kekre <[email protected]> wrote:

> I think the original design for shutdown was to start killing from input
> operator side and have it go through the DAG. Though, I have not looked at
> that in a while. Thomas would know the details.
>
> Thks,
> Amol
>
>
> On Tue, Jan 26, 2016 at 2:40 PM, Timothy Farkas <[email protected]>
> wrote:
>
> > Hello all,
> >
> > If an Apex app is Shutdown (as opposed to killed) is there a guarantee
> that
> > all the operators will reach the last window produced by an input
> operator
> > and that committed will be called for that last window before the
> > application is terminated?
> >
> > Thanks,
> > Tim
> >
>