On Wed, Sep 3, 2008 at 4:47 PM, Linus Tolke <[EMAIL PROTECTED]> wrote:
> I would like the issue 5355 (the only P2 issue) to have a plan before we do
> the second beta so I will to tomorrow evening and not do the release today.

Not all of my Eclipse workspaces for ArgoUML include the www tree, so
the only time I see that the schedule has been changed is when it's
announced on the list.

I'm not sure when the current schedule was created, but it doesn't
seem reasonable to me to have a two month alpha period followed by ONE
WEEK beta period.  For a beta test to be effective, the users have to
have time to get the announcement, schedule the testing in among their
regular work, then report the results back to us.

Even if we were to convince ourselves that we'd get effective end user
testing (and reporting of those tests) in a week, surely you can't
start the clock until the release has actually been announced (which
it hasn't yet).

Tom

---------------------------------------------------------------------