Hello everyone! As per the previously agreed-upon schedule for Beam releases, the process for the 2.6.0 Beam release should start on July 17th.
I volunteer to perform this release. Here is the schedule that I have in mind: - We start triaging JIRA issues this week. - I will cut a release branch on July 17. - After July 17, any blockers will need to be cherry-picked into the release branch. - As soon as tests look good, and blockers have been addressed, I will perform the other release tasks. Does that seem reasonable to the community? Best -P. -- Got feedback? go/pabloem-feedback