Hi All,

I would like to announce that only critical/blocker or any stabilization
fixes will be accepted on the main branch from now onwards. If you have any
PRs that are ready to be merged into 4.21 (with review & tests completed),
please let me know or ping me (@sureshanaparti) on GitHub.

I'll work towards stabilization, and would like to cut 4.21.0 RC1 early
next week (and further RCs if necessary) & start the voting / release
process.

Looking forward to your support. Thanks.

Regards,
Suresh

On Mon, Jul 14, 2025 at 7:22 PM Suresh Kumar Anaparti <
sureshkumar.anapa...@gmail.com> wrote:

> Hi All,
>
> We've so far closed 109 Issues and PRs in the 4.21.0 milestone [1]. There
> are still some targeted items to finish, so I would like to postpone the
> 4.21.0 release for at least a week.
>
> Here is the updated timelines:
>
> - (Ongoing) till last week of Jul 2025: Accept all PRs for the bug fixes,
> improvements, features
> - (1 week) last week of Jul 2025: Accept any critical/blocker fixes and
> stabilise main/4.21 branch
> - (1 week) end of Jul 2025, first week of Aug 2025 onwards: Cut 4.21.0 RC1
> (and further RCs if necessary), start & conclude vote, and finish release
> work
>
> Looking forward to your support, mainly on the reviews & tests for the
> outstanding PRs [2]. Also, please resolve any conflicts in your PRs,
> address the outstanding comments and share the test results. Thanks.
>
> Please let me know if you have any feedback, thoughts.
>
> [1] https://github.com/apache/cloudstack/milestone/35
> [2]
> https://github.com/apache/cloudstack/pulls?q=is%3Aopen+is%3Apr+milestone%3A4.21.0
>
> Regards,
> Suresh
>
> On Thu, Jun 5, 2025 at 6:16 PM Suresh Kumar Anaparti <
> sureshkumar.anapa...@gmail.com> wrote:
>
>> Hi All,
>>
>> It's been a few months since the proposal, and we've so far closed 62
>> issues and PRs in the 4.21.0 milestone [1]. Currently, we've 208 open items
>> in the 4.21.0 milestone, tracked/triaged through the GitHub project 'Apache
>> CloudStack 4.21.0' [2]. Ping me (@sureshanaparti) on your issues and PRs
>> that are to be included in 4.21.0, if these are not in the milestone /
>> project.
>>
>> 4.21.0 release is proposed as a Regular (non-LTS) [3] release with the
>> following timelines, aiming to start the RC/vote by the end of Jul 2025:
>>
>> - Now until mid-July 2025: Accept all PRs for the bug fixes,
>> improvements, features
>> - Until last week of Jul 2025: Accept any fixes and stabilise main/4.21
>> branch
>> - Last week of Jul 2025: Cut 4.21.0 RC1 (and further RCs if necessary),
>> start & conclude vote, and finish release work
>>
>> Please let me know if you have any feedback, thoughts. Looking forward to
>> your support on bug fixes, reviews, and tests. Thanks.
>>
>> [1] https://github.com/apache/cloudstack/milestone/35
>> [2] https://github.com/orgs/apache/projects/503
>> [3] https://cwiki.apache.org/confluence/display/CLOUDSTACK/LTS
>>
>> Regards,
>> Suresh
>>
>> On Mon, Feb 3, 2025 at 6:48 PM Suresh Kumar Anaparti <
>> sureshanapa...@apache.org> wrote:
>>
>>> Hi All,
>>>
>>> I want to propose and put myself forward as the release manager for
>>> 4.21.0 if there are no objections. I've previously RM'd 4.16.1.0 & 4.19.1.0
>>> releases, and co-RM'd some releases before that. I hope that experiences
>>> will help me here, for a successful release.
>>>
>>> I think, for 4.21.0, we can accept any features, improvements and bug
>>> fixes in the next few months until May-2025, and aim to cut RC in Q2 2025
>>> (sometime in Jun-2025). Please ping me (@sureshanaparti) on GitHub, in case
>>> you want to include any Issues/PRs in 4.21.0. I'll propose the timeline
>>> details soon.
>>>
>>> I hope to have your support. Please let me know if you have any
>>> thoughts/comments.
>>>
>>> Regards,
>>> Suresh
>>>
>>

Reply via email to