Following up on a our discussions about LTS [1], post 4.9 releases [2], and 
5.0.0/6.0.0 [3], I have assembled a release plan for the next 18-20 months in 
the wiki [4].  My original proposal assumed by that 4.9 would be released by 1 
July.  I have adjusted the timelines assuming that we will complete the release 
by 15 July.  My thinking is that the number of defect fixes present in 4.9 and 
4.8.1 would require more than 2 weeks of work to backport to a 4.8-based LTS.  
Therefore, I have shifted the LTS cutoff dates from 1 Jan and 1 July to 15 Jan 
and 15 July.

Once we gain consensus on the release cycle and calendar, I will cleanup the 
wiki to move completed release plans to an archive area and remove obsolete 
release process documentation.

Thanks,
-John

[1]: http://markmail.org/thread/zzrjldiryhy3ygfk
[2]: http://markmail.org/thread/7rv3jwz4hzf3yplf
[3]: http://markmail.org/thread/c24hvshz3z4babjb
[4]: 
https://cwiki.apache.org/confluence/display/CLOUDSTACK/%5BPROPOSAL%5D+2016-2017+Release+Cycle+and+Calendar<https://cwiki.apache.org/confluence/display/CLOUDSTACK/[PROPOSAL]+2016-2017+Release+Cycle+and+Calendar>

john.burw...@shapeblue.comĀ 
www.shapeblue.com
53 Chandos Place, Covent Garden, London VA WC2N 4HSUK
@shapeblue
  
 

Reply via email to