All,

With 4.14.1.0 released and announced yesterday, I propose an rough timeline for:

4.15.1.0 release: target for Q2 2021
(4.5 weeks) ongoing - 2 April 2021: accept all bugs, issues, improvements 
allowed in LTS [1]
(2 weeks) 8 April - 19 April 2021: accept only critical/blocker fixes
(1 week) 19 April - 23 April 2021: stabilise 4.15 branch, accept only blocker 
issues if any
WC 26 April - onwards - Cut 4.15.1.0 RC1 and further RCs if necessary, 
start/conclude vote, and finish release work

4.16.0.0 release: target for Q3/Q4 2021
Let's discuss the actual timeline after 4.15.1.0 and if anyone else wants to 
volunteer as the RM.


[1] https://cwiki.apache.org/confluence/display/CLOUDSTACK/LTS


Thoughts? Thanks.