On Tue, May 4, 2010 at 11:23 AM, Jacob Beard <jbea...@cs.mcgill.ca> wrote:
> Hi,
>
> I'd like to start populating JIRA with tasks and milestones related to
> my GSoC project,
<snip/>

+1

> and I'm wondering what is the best way to go about
> this. I think these tasks should go under the SCXML project in
> JIRA[1], but I'm not sure if I should do more to differentiate them as
> a separate sub-project.
>
<snap/>

One option is to create sub-tasks for the original issue you have,
SCXML-115 [1] (see LHS menu).

This will create separate issues in JIRA for each task, so they can be
managed independently, but it will also neatly roll everything up
under the above umbrella issue. For an example of this (from another
project), see ATTIC-1 [2].

What do you think about using this approach?

-Rahul

[1] https://issues.apache.org/jira/browse/SCXML-115
[2] https://issues.apache.org/jira/browse/ATTIC-1


> Please let me know what you think. Thanks,
>
> Jake
>
> [1] https://issues.apache.org/jira/browse/SCXML
>

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscr...@commons.apache.org
For additional commands, e-mail: dev-h...@commons.apache.org

Reply via email to