Just wanted to start the process for the 3.2.0 release. Created the master
issue at https://issues.apache.org/jira/browse/CB-5155

I know some people are focused on getting 2.9.x out the door currently.
That should take priority over this release I believe.

Rough Timeline I had in mind

Oct 24
- Plugins release + Announce

Oct 25/28
- 3.2.0 RC tag
- 3.2.0-0.1.0 CLI RC release (push to npm but don't set to latest)
- Plugman release (might not have to release an rc for this) + push to npm

Oct 28-Nov 1
- Test
- Draft release blog post (include snap shot of plugin versions that were
tested)

Nov 4
- 3.2.0 Final tag
- Tag CLI and push to npm as latest
- Announce

Nov 7
- Plugins release (if necessary) + Announce

How do people feel about this timeline?