On Sun, Jun 6, 2021 at 3:28 PM 王峰 <[email protected]> wrote:

>
>
>
> 非常开心收到dolphinscheduler 开发者邮件,这次提问主要是因为上传文件问题,dolphinscheduler
> 大部分已经满足实际需求,但也有使用时候遇到些问题,目前,主要发现两个问题:
> 1、上传文件只能是文件而不是文件夹;
> 2、上传资源只能单独授权某一个用户,维护成本高;
>
>
>
>
>
>
>
>
>
>
>
>
>
>
> 在 2021-06-05 23:21:30,"Lidong Dai" <[email protected]> 写道:
> >hi,
> >  any progress? Do we need a meeting to solve this?
> >By the way, the picture can't show in the apache mailing list, you can
> >upload the pic to github, then paste the url address to the mail.
> >
> >
> >Best Regards
> >---------------
> >DolphinScheduler PMC
> >Lidong Dai
> >[email protected]
> >---------------
> >
> >
> >On Tue, Jun 1, 2021 at 5:04 PM Xingjie Wang(联通集团联通数字科技有限公司) <
> >[email protected]> wrote:
> >
> >> This really doesn't satisfy those scene.
> >> For the first one ,If we want to do this, we should save the varPool to
> >> the level of processInstance, so the Task4 can get the varPool from
> Task1
> >> and do not by Task2 and Task3.
> >> This one will obscure the relation between globalParam and localParam
> and
> >> varPool.
> >> Other plan ,when user define the Task4 IN param ,user should chonse the
> >> Task1 that this param is the Task1's OUT param .When init the Task4's
> >> varPool ,get the Task1 form completeTaskList,then get the varPool.And
> when
> >> the taskInstance have a new property, mark this taskInstance'name into
> this
> >> property ,and put this property into the varPool.
> >> It will satisfy those scene.
> >> How do you think?
> >> -----邮件原件-----
> >> 发件人: Ruan, Wenjun <[email protected]>
> >> 发送时间: 2021年6月1日 16:07
> >> 收件人: [email protected]
> >> 主题: Re: [DISCUSS]The new Plan of global params
> >>
> >> Sorry, it seems that the picture cannot be displayed well, the dag
> >> structure is as follow:
> >>
> >> Task1   ->  Task2   ->  Task3   ->  Task4
> >>
> >> From: Ruan, Wenjun <[email protected]>
> >> Date: Tuesday, June 1, 2021 at 3:55 PM
> >> To: [email protected] <[email protected]>
> >> Subject: Re: [DISCUSS]The new Plan of global params External Email Hi
> >> Xingjie,
> >>
> >> I have two things want to confirm.
> >> In your plan it seems that we need to store varpool in all the post
> nodes?
> >> For example, if I have a simple dag like below:
> >> [cid:[email protected]]
> >>
> >> If I want to get the out param of Task1 in Task4, for example we call it
> >> parameterA, then we need to store parameterA in Task2’s varpool and
> Task3’s
> >> varpool, even if we don’t need parameterA in Task2 and Task3, am I
> right?
> >> Can we take it directly from Task1?
> >>
> >> The second thing is that if I want to troubleshouting, can I find the
> >> source of the parameters in the varpool? It seems I need to look forward
> >> and find the first node that contains the parameter? It seems not
> >> convenient, if I have much tasks in a dag.
> >>
> >> Thanks,
> >> Wenjun Ruan
> >>
> >>
> >> From: Xingjie Wang(联通集团联通数字科技有限公司) <[email protected]>
> >> Date: Tuesday, June 1, 2021 at 3:21 PM
> >> To: [email protected] <[email protected]>
> >> Subject: [DISCUSS]The new Plan of global params External Email
> >>
> >>
> >>
> >> Hi Dev Team
> >>
> >> The scheme of The global params that Task need change as blow。
> >> Here is the ISSUE about this DISCUSS。
> >>
> >>
> https://nam10.safelinks.protection.outlook.com/?url=https%3A%2F%2Fgithub.com%2Fapache%2Fdolphinscheduler%2Fissues%2F5565&amp;data=04%7C01%7Cweruan%40ebay.com%7C71c6b15115994fd6463808d924cdbf7b%7C46326bff992841a0baca17c16c94ea99%7C0%7C0%7C637581288947116284%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000&amp;sdata=Na6C8tAQODl%2BrfThuaGmtCcVqqwt1eSBpQTFgaRuVXc%3D&amp;reserved=0
> >> <
> >>
> https://nam10.safelinks.protection.outlook.com/?url=https%3A%2F%2Fgithub.com%2Fapache%2Fdolphinscheduler%2Fissues%2F5565&data=04%7C01%7Cweruan%40ebay.com%7C2a73397f8b394100b21508d924d28b37%7C46326bff992841a0baca17c16c94ea99%7C0%7C0%7C637581309371279320%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000&sdata=1B%2BKIBz%2BCfhTp0nRiK3oKFz4KKgYQDN%2B46xF091o0BQ%3D&reserved=0
> >> >
> >>
> >> I will change the scheme of global param that depend on the relation of
> >> the task.
> >> Here is the detail about this .
> >>
> >> 1.     create taskInstance
> >>
> >> Get the previous tasks ,get the varPool of those tasks, put those into
> >> this varPool. If the previous task has the same varPool name,use the
> value
> >> that is not null.If all of the  values  are null, use the earlier one.
> >>
> >>   1.  Worker get the param
> >>
> >> Master will send the varPool to the Worker ,and taskPorcessor get the
> >> varPool with the format of List<Property>, varPool will do the same as
> the
> >> localParam.
> >>
> >>   1.  Worker response out Parm
> >>
> >> When the user define the OUT param in the page of Task Definition.Worker
> >> will get the result of Processor .
> >>
> >> The different Processor return the different format ,for example SQL
> >> return the format of List<Map<String,String>>,users could get more than
> one
> >> line or more than one column;SHELL get the Map<String,String> or
> >> String.This out Param will add into the varPool ,and send to the Master
> >> ,save into the databases.Also ,this value will save into the localParam
> >>
> >>
> >>
> >> If you have some question or have the better plan ,please contact me
> >> .thank you.
> >>
> >> 如果您错误接收了该邮件,请通过电子邮件立即通知我们。请回复邮件到 [email protected]
> ,即可以退订此邮件。我们将立即将您的信息从我们的发送目录中删除。
> >> If you have received this email in error please notify us immediately by
> >> e-mail. Please reply to [email protected] ,you can unsubscribe
> from
> >> this mail. We will immediately remove your information from send
> catalogue
> >> of our.
> >> 如果您错误接收了该邮件,请通过电子邮件立即通知我们。请回复邮件到 [email protected]
> ,即可以退订此邮件。我们将立即将您的信息从我们的发送目录中删除。
> >> If you have received this email in error please notify us immediately by
> >> e-mail. Please reply to [email protected] ,you can unsubscribe
> from
> >> this mail. We will immediately remove your information from send
> catalogue
> >> of our.
> >>
>