https://issues.apache.org/jira/browse/FALCON-1371?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
]
Balu Vellanki updated FALCON-1371:
----------------------------------
Description:
Create a process entity with
- frequency of 1 hour
- validity start as "2012-07-01T00:00Z"
- and validity end as "2012-07-01T01:02Z"
Now list the process entity after one hour. The process bundle status in Oozie
is shown as "succeeded". But Falcon shows the status as submitted.
was:
Create a process entity with
- frequency of 1 hour
- validity start as "2012-07-01T00:00Z"
- and validity end as "2012-07-01T01:02Z"
Now list the process entity after one hour. The process coordinator status in
Oozie is "succeeded". But Falcon shows the status as submitted.
> Status of scheduled Process entity is shown as submitted in corner case
> -----------------------------------------------------------------------
>
> Key: FALCON-1371
> URL: https://issues.apache.org/jira/browse/FALCON-1371
> Project: Falcon
> Issue Type: Bug
> Affects Versions: 0.6.1
> Reporter: Balu Vellanki
> Assignee: Balu Vellanki
> Attachments: FALCON-1371.patch
>
>
> Create a process entity with
> - frequency of 1 hour
> - validity start as "2012-07-01T00:00Z"
> - and validity end as "2012-07-01T01:02Z"
> Now list the process entity after one hour. The process bundle status in
> Oozie is shown as "succeeded". But Falcon shows the status as submitted.
--
This message was sent by Atlassian JIRA
(v6.3.4#6332)