Hi everyone,

I want to propose shipping Geode on a regular cadence. My concrete proposal
is to ship Geode every 3 months on the first weekday. To make sure we hit
that date we would cut the release 1 months prior to that day.

*Why?*
Knowing on what day the release will get cut and on what day we ship allows
community members to plan their contributions. If I want my feature to be
in the next release I know by when I need to have it merged to develop and
can plan accordingly. As a user who is waiting for a particular feature or
fix that's already on develop, I know when to expect the release that
includes this work and again, can plan accordingly.

This makes working and using Apache Geode more predictable which makes all
our lives less stressful. To make this work, it's important to be strict
about cutting the release branch on the set date and only allow critical
fixes after the release has been cut. Once we start compromising on this,
we go down a slippery slope that ultimately leads to not getting the
predictability benefits described here.

Some other successful Apache projects share similar approaches:

   - Kafka
   <https://cwiki.apache.org/confluence/display/KAFKA/Future+release+plan>
   releases every 4 months and cuts the release 1 month prior
   - PredictionIO <https://predictionio.apache.org/resources/release/> releases
   every 2 months
   - Spark <https://spark.apache.org/versioning-policy.html> does not seem
   to have a hard date, but aims to ship every 6 months, so there is at least
   a goal date


*What?*
As stated above, I suggest to release every three months. Given we just
shipped the next release would go out on January 2nd. That timing in
unfortunate, due to the holidays. Therefore I propose to aim for a December
3rd (1st Monday in December) release. In order to meet that date, we should
cut the release branch on November 1st. That also means that we should
start finding a volunteer to manager the release on October 25th. I know
this seems really close, given we just shipped, but keep in mind that this
is to avoid the holidays and that we already have close to a month worth of
work on develop.

*Proposed near future schedule:*
October 25th: Find release manager
November 1st: Cut 1.8 release branch
December 1st: Ship 1.8
January 28th: Find release manager
February 1st: Cut 1.9 release branch
March 1st: Ship 1.9
and so on...