Alright, we have closed all the JIRA issues and successfully ran all the TCK tests.
Time for the "final stuff" On Mon, Jul 25, 2005 at 04:59:47PM -0500, David Blevins wrote: > THE FINAL STUFF > > We have to run the TCK on the final binary, which means we need to > allow for a couple days of just testing the actual geronimo-1.0- > M4.zip that people will download. To even get that far, we need to: > > 1. [notes] Create release notes for M4 and check them into the QA > branch > 2. [svn] Close the QA branch and copy it to tags/v1_0_M4 > 3. [dist] Cut and sign the binary and source distributions > Aaron cleared up 1. I'm going to take care of 2 and 3. We should have binaries up shortly for voting and one final TCK sweep. -David