I think we've made significant progress in the last week towards being
ready to make the branch for M5, but I think there may be reasons to
wait a couple more days. There are 2 features that people want to get
in (security improvements and DDL generation) that I would like to see
in M5, and more stabilization is needed in any case before the release.
I think that unless someone is waiting to get a new feature in that
shouldn't go in M5 we should wait until monday and see where we are.
If anyone is contemplating a commit that may destabilize our code
please speak up so we can branch beforehand.
thanks
david jencks
On Sep 6, 2005, at 9:33 PM, Jeff Genender wrote:
Ok ...I am hijacking this thread... enough discussion...lets vote on
it...
[ ] Friday 9/9 is the QA Cut date
[ ] I think it should be after Friday...and should be on ______
For me:
[X] Friday 9/9 is the QA Cut date
David Blevins wrote:
On Sep 6, 2005, at 6:50 PM, Jeff Genender wrote:
Aaron Mulder wrote:
What is the point of the "frozen list"? At this point, it
doesn't appear to have stopped development of things that aren't
on the list.
The list for what we are agreeing to go into M5. If something
isn't on the list and its an added bonus, then fine. We need a
closure date at this point. I think we have all agreed what is
minimally in the cut.
Maybe we should make the branch like Friday, so any code not on
the list has to go into HEAD, and just have a longer closing
period to
resolve the list items. There is a lot on the list, so that would
mean a
lot of merges to HEAD, but unless everyone is willing to hold off on
non-list items, I'm not sure we're actually moving toward greater
stability in the mean time.
Ok..shall we branch on Friday? Anhyone have any issues with this?
I am game.
Friday is great. Aaron expressed the same concern I was thinking
about; getting further and further from stable the long we wait to
branch. Things always tend to creep in.
+1
David