On Dec 6, 2005, at 11:51 AM, David Jencks wrote:


On Dec 6, 2005, at 11:10 AM, Donald Woods wrote:

Matt Hogstrom wrote:
All,
We've made a lot of progress over the weekend and the past few days in terms of testing, bug fixing as well as new features. At this point though we are running out of time and need to shift from features to finish and testing to make sure we're putting out the best offering we can. Given that there are a few things we need to do and I need your help. First, we need to manage our way out of the outstanding 98 JIRAs for 1.0. I would like to ask everyone that has a JIRA for 1.0 (either reported by you and unassigned or assigned to you) to please quickly review it and prioritize it appropriately. The assignment should be:
1.0 (absolutely needs to be in ... stop ship if its in this category)
1.1 (important but can be addressed later)
1.x (sooner than later but not immediately urgent)
wishlist (self explanatory)
Please do this today. If you absolutely cannot let me know and I'll defer them for you :) Because we need to finish TCK testing as well as test the packaging and installer I would like to make today the last day for fixing function / features.. I propose we cut a 1.0 branch tonight so we can fix things like missing content in the console and other items that will be removed from Geronimo that need to remain in HEAD for further development. Also, we will make the final cutover of versions from SNAPSHOTs to their released versions for TranQL, Open EJB, and Axis. I think we have everything else taken care of. Preferrably it would be great if we can start a vote on Friday for a release assuming we get the remaining work completed. Please respond to this e-mail with outstanding urgent issues that need to be completed. Here is a start for this activity:
* Remove broken / non-functional links in the console
* Installer work completed
* Testing of sample apps to ensure we have not regressed

  * Continued build problems due to "new" maven goals

These continue but seem to subside after removing all traces of old plugins and building twice.
  * Remove links to Confluence on the Welcome page
  * Are we going to include the TranQL Connectors for Oracle and DB2?

I would rather not include the oracle connector since I don't think it has been tested in the last year or so. Matt would be able to advise on the stability of the db2 connector. I would rather not include them unless we are quite confident they work reliably.

- hot deploy config (easy)
DONE
- dtds included in schema directory (pretty easy)
- online deployer. I think this is basically a packaging issue at this point, but I haven't started trying to make it work
DONE
- shutdown jar DONE
- offline deployer. I would rather release this set of tools in a week or so when we have had more of a chance to discuss how they should work. I have the start of new deployer and assembly command line tools based on the packaging and assembly plugins on my machine, but it is unlikely that any interface I come up with to run them will be considered usable by anyone else.

- trade app >> applications
-- more sample apps???

thanks
david jencks

thanks
david jencks


I'm sure there are lits of other items. Let's get them in here and I'll update the release managemetn page.
Thanks,
Matt