Sounds good, +1 for M2, which will make people notice we are progressing :)

As we've finished SQL module APIs(cheers! :) ), I notice that there're
still over 2 percent of  APIs are missing in Harmony, this may be a
target for us in the near future;
Stablity and Performance is another issue we shall deal with, perhaps
we can start run some benchmark, and improve code for Harmony;
Till now, Java 6 is still in plan, but it may be a proper time to do
some work on it now. How to publish our java 6 branch can also be a
topic :)

2007/6/4, Mikhail Loenko <[EMAIL PROTECTED]>:
it has been a while since we made our first milestone...

Since that we have already fixed 250+ issues and we are continuing
doing good job :)

Let's plan the next release. We had some discussion on desired frequency
of the milestones and I saw opinions 1 month, 2 months, 1 quarter. So that
2mo seems to be an average.

If we go with 2mo interval, than M2 should be somewhere
at the end of June. I suggest that we agree on some date and then
agree what should be our focus for M2.

After that we review current bugs and mark those that we want to fix
by the milestone.

My opinion wrt the focus is we should continue improving stability
as measured by ability to run real apps. And we probably should fight
against crashes as the most annoying type of failures.

opinions?

Thanks,
Mikhail



--

Best Regards!

Jimmy, Jing Lv
China Software Development Lab, IBM

Reply via email to