Hi, OK, at least nobody suggested that we have longer then 3-month schedule. That means that we should have next milestone no later then September, 30.
So I'd like to remind that we are close to the mid of September and propose the following M3 schedule: - Septemer 15: feature freeze - svn trunk is frozen I think this time it makes sense to freeze the trunk instead of branching to avoid doing merges for bugfixes - Septemer 22: code freeze - M3 branch(tag?) is created and the trunk is unfrozen. All fixes for M3 go to the branch. - Septemer 29 :release date - M3-branch is merged with the trunk. Objections? Thanks, Stepan Mishura Intel Enterprise Solutions Software Division