OK. Code Freeze 10th December Publish 17th December On Tue, Dec 7, 2010 at 6:48 PM, Tim Ellison <t.p.elli...@gmail.com> wrote:
> On 06/Dec/2010 15:31, Ray Chen wrote: > > Sure, I propose the following dates: > > > > Feature Freeze Wed 15th December > > Code Freeze Wed 22nd December > > Publish Wed 29th December > > Unless somebody shouts, I don't think we need to adopt a length feature > freeze. I don't see any major work in flight at the moment. So how > about code freeze sooner (say Dec 10th) and publish the net milestone a > week later (Dec 17th)? > > > Please help to run the tests. > > > > Tim, > > I found Kevin has attached a patch for > > https://issues.apache.org/jira/browse/HARMONY-6419, would you please > help > > to review it? > > Sure. If others want to review it too that is fine ;-) > > Regards, > Tim > > > Let's make new milstones for the coming New Year! :) > > > > On Mon, Dec 6, 2010 at 6:22 PM, Tim Ellison <t.p.elli...@gmail.com> > wrote: > > > >> On 30/Nov/2010 13:55, Ray Chen wrote: > >>> Hmmm... Ok, I think it will take some time to understand these for some > >> time. > >>> Maybe we should put this milestone off for serveral days before I > >>> understand all the process. > >> > >> Hi Ray, > >> > >> Thanks for volunteering to do some RM. I can also help with the > process. > >> > >> How about we set a new proposed date for the next milestone, and work > >> towards that? Encouraging people to report test results and getting the > >> list of JIRA must fixes sorted would be the first step. > >> > >> Regards, > >> Tim > >> > >> > >>> On Tue, Nov 30, 2010 at 5:38 PM, Mark Hindess > >>> <mark.hind...@googlemail.com> wrote: > >>>> > >>>> In message < > >> aanlktimb6ffnvpgmstycklxmnm5znmmeksxjopxs6...@mail.gmail.com>, > >>>> Ray Chen writes: > >>>>> > >>>>> Hi Mark, > >>>>> Does release manager must be a PMC? > >>>> > >>>> No. See: > >>>> > >>>> http://www.apache.org/dev/release-publishing.html#release_manager > >>>> > >>>>> If not, maybe I can take the responsibility. > >>>> > >>>> That would be great. > >>>> > >>>>> However, I don't know much about how to do it, I think we need some > >>>>> transferring work. > >>>> > >>>> Ask here if you have questions. My activity as release manager for > >>>> previous releases was something like ... > >>>> > >>>> Suggest dates, announce freezes, encourage people to do testing and > >>>> move things along a bit when people send test results, work to resolve > >>>> release critical issues, produce signed source artifacts, start a > vote, > >>>> conclude the vote and produce signed binaries. > >>>> > >>>> The scripts I use to create linux source and binary artifacts are in > svn > >>>> at: > >>>> > >>>> https://svn.apache.org/repos/asf/harmony/standard/tools/release > >>>> > >>>> I do the equivalent manual process for both windows platforms. > >>>> > >>>> The last crucial part is populating the /dist/ tree for mirroring. > >>>> You need to be careful doing this so as to avoid messing up lots of > >>>> mirrors. I tend to make the tree elsewhere then check that it matches > >>>> the size/shape of the previous release tree before using rsync to put > >>>> it in to /dist/. > >>>> > >>>> Just ask if you have question about any of the process. > >>>> > >>>> Regards, > >>>> Mark. > >>>> > >>>> > >>>> > >>> > >>> > >>> > >> > > > > > > > -- Regards, Ray Chen