Hello,

after extensive discussions on this topic, I would like to call for a vote on the follow proposal:


- We do Kafka releases on a fixed time schedule, to avoid timeline drifts and to ensure that we are doing 3 release per year

- We want to accommodate major holidays across the globe, while trying to make every release roughly a 4-months cycle.

- We want to reduce the time windows between KIP, feature, and code freeze to ensure a more streamlines release delivery


Concretely:

 - We propose a 3 week window between KIP freeze and feature freeze

 - We propose a 2 week window between feature freeze and code freeze

 - KIP/feature/code freeze will each be on a Wednesday

 - KIP freeze will be on fixed calendar weeks, namely
   * week 9
   * week 25
   * week 41

 - We will follow this new release cycle starting with the 4.7 release

- We already have a 4.5 release plan, and don't change it. KIP freeze is set to Jan/13/2027

- To transit into the new schedule, we will have KIP freeze for 4.6 release on June/2/2027


Outlook for 2028 (assuming we continue 4.x release series):

  - AK 4.7 KIP freeze: March/9
  - AK 4.8 KIP freeze: Jun/21
  - AK 4.9 KIP freeze: Oct/11


If this proposal gets accepted, we will update the corresponding release wiki pages accordingly.


Thanks a lot,
  -Matthias