After a build job be submit, please click the ³Jobs² tab, where shows the
job status, you can see a new job there with state ³Pending² or ³Running²;
Click to expand and then see each step of the job; If the job is completed
successfully, the cube¹s status will be updated from ³Disabled² to
³Active², then you will be able to write SQL in the ³Query² tab to get the
result; If job is failed, need check the error, fix the issue and then
resume the job;

Just let me know if I didn¹t get your point. Thanks for evaluating Kylin!

On 7/2/15, 9:29 PM, "Karempudi Ramarao" <[email protected]> wrote:

>Thank you. We have taken those steps; it says that Build is submitted
>successfully but the job then gets disabled. When we try to enable it, we
>get the error that no ready segment is there. What does that mean? It
>looks like we are missing something in the definition of the cube but
>there is not even a hint what it may be.
>
>Ram
>
>-----Original Message-----
>From: ShaoFeng Shi [mailto:[email protected]]
>Sent: Thursday, July 02, 2015 1:42 AM
>To: [email protected]
>Subject: Re: Error Creating cube
>
>Did you build the cube? After a cube be created, you need build it: click
>"Actions" -> "Build", then select a date range t(if your cube is
>partitioned);
>
>2015-07-02 8:16 GMT+08:00 Yaseen Mohammed <[email protected]>:
>
>>  Hi,
>>
>>      I have installed Kylin on Mapr and able to access hive tables and
>> were able to  create project and cube but  cube is in disable mode
>> when I am trying to enable it is throwing up with an error cube does
>> not contain READY segment can you please throw some light on this.
>> This is the first time I am creating cube.
>>
>> Thanks,
>>
>> Yaseen
>>
>>
>>
>>
>>
>>