David Smiley updated SOLR-9080:
-------------------------------
    Affects Version/s: 6.0
        Fix Version/s:     (was: 6.0)
                       6.1

> DateMath is broken before the year 1582
> ---------------------------------------
>
>                 Key: SOLR-9080
>                 URL: https://issues.apache.org/jira/browse/SOLR-9080
>             Project: Solr
>          Issue Type: Bug
>    Affects Versions: 6.0
>            Reporter: David Smiley
>            Assignee: David Smiley
>             Fix For: 6.1
>
>         Attachments: SOLR_9080_DateMath_should_not_use_Calendar_API.patch
>
>
> In Solr 6.0, dates are parsed using the Java 8 java.time API.  It formerly 
> was parsed using java.util.SimpleDateFormat which uses 
> java.util.GregorianCalendar.  I've learned that the java.time API does _not_ 
> switch to a different algorithm at the Gregorian Change Date (year 1582) 
> whereas GregorianCalendar does.  A ramification of this is that the 
> milliseconds before epoch value is different between the APIs for dates prior 
> to this year.  They both round-trip between themselves but not between each 
> other prior to this date.  Thus, anyone indexing historical dates must 
> re-index when moving to Solr 6.
> What was _not_ changed in the parsing code was Solr's date-math logic -- it 
> still uses the Calendar API.  This works for dates after 1582 but before, 
> it'll introduce discrepancies.  Here's an example showing weird behavior:
> http://localhost:8983/solr/techproducts/select?facet.range.end=1400-01-01T00:00:00Z&facet.range.gap=%2B10YEARS&facet.range.start=1300-01-01T00:00:00Z/YEAR&facet.range=manufacturedate_dt&facet=on&indent=on&q=*:*&rows=0&wt=json
> Note that the year 1300 rounded down to the year, becomes 1299 January 8th 
> (weird in and of itself) and that subsequent gaps start on the 9th.
> {noformat}
> "counts":[
>           "1299-01-08T00:00:00Z",0,
>           "1309-01-09T00:00:00Z",0,
>           "1319-01-09T00:00:00Z",0,  ...
> {noformat}
> This weirdness will show itself for units at the year or month level, but not 
> below that (from what I'm seeing).  In other words, if facet.range.gap is at 
> this amount, or otherwise using the date math syntax to round or add a year 
> or month, there will be issues like this.  Otherwise there doesn't seem to be 
> an issue.
> I think the solution is clearly to switch the date math code to use the 
> java.time API.



--
This message was sent by Atlassian JIRA