Hi,

In 9.x there's still the backport of https://github.com/apache/lucene/pull/13570 to be done. The PR apperas in the changelog, but was not backported yet. Chris and I will do this soon.

9.last release on Sept 22 fits perfectly with the JDK 23 release (and we will have Panama Vector Support). I am seeting up Jenkins Job with latest RC now to verify all vector stuff works with 23.

Uwe

Am 08.08.2024 um 18:50 schrieb Adrien Grand:
Hello everyone,

As previously discussed <https://lists.apache.org/thread/4bhnkkvvodxxgrpj4yqm5yrgj0ppc59r>, I plan on releasing 9.last and 10.0 under the following timeline:
- ~September 15th: 10.0 feature freeze - main becomes 11.0
- ~September 22nd: 9.last release,
- ~October 1st: 10.0 release.

Unless someone shortly volunteers to do a 9.x release, this 9.last release will likely be 9.12.

As these dates are coming shortly, I would like to start tracking blockers. Please reply to this thread with issues that you know about that should delay the 9.last or 10.0 releases.

Chris, Uwe: I also wanted to check with you if this timeline works well with regards to supporting Java 23 in 9.last and 10.0?

--
Adrien

--