June 1 is day after tomorrow and we are not making progress on any of
the outstanding JIRAs. Testing sentiment again on 0.7...
On 5/23/12 7:48 AM, Grant Ingersoll wrote:
On May 22, 2012, at 12:33 PM, Jeff Eastman wrote:
We still have 11 open issues that are preventing us from entering code freeze.
Of these, 6 are marked as low priority and only one is marked as critical. Do
we want to:
A - punt all non-critical issues to 0.8
B - punt all low priority issues to 0.8 and wait for the others to be resolved
C - punt all open issues to 0.8 and get on with the release
D - delay the target date for code freeze until 1 June and reassess then
Sorry for being out on this one, as I've had a rather large deadline at work.
My vote is for D.