Another way to approach things is to take a look at the Rat report and to
see which files are left to be done and then to do those, first figuring
out who is assigned to the related module and seeing what the hold up is,
etc.

Gj

On Mon, Oct 30, 2017 at 4:18 PM, Geertjan Wielenga <
[email protected]> wrote:

> Great and congrats!
>
> I think anything not marked 'Done' should be something that could be
> looked at.
>
> Also, I think anything marked to 'jkostaras' has been looked at, but not
> fixed -- you could take over those items, for example.
>
> Also, I've assigned everything in 'apisupport' to myself, that area could
> also be something to look at and check and take over.
>
> Many thanks for your hard work.
>
> Gj
>
> On Mon, Oct 30, 2017 at 4:15 PM, Lars Bruun-Hansen <[email protected]
> > wrote:
>
>> I've done 5-6 modules.
>> Now - for the first time - all modules have a name next to them. (except a
>> few o.eclipse but I'm under that Antonio Vieiro is looking at those?).
>>
>> I'll be happy to do more if someone has signed up for more than they can
>> chew.  :-)
>> Let me know.
>>
>
>