On 9/26/07, Tammo van Lessen <[EMAIL PROTECTED]> wrote:
>
> Hi all,
>
> a student at our institute is currently developing a monitoring tool
> for Ode which enables browsing process instances and visualizing
> process models and the state of their activities.
>
> That actually works quite well with one exception: the current
> activity state model does not consider disabled activities. That means
> that DPE cannot be visualized by the monitoring tool.
>
> Therefore I propose to introduce a new state to activities so that we
> have ENABLED, STARTED, COMPLETED, FAILURE and DISABLED (or
> DP-ELIMINATED?)
>
> What do you think? If there are no objections I'll file a jira and
> will implement it for the trunk (and a patch for Ode 1.1)


Sounds good to me.What about calling it DEAD to make sure we don't confuse
it with another state later on?

Matthieu

Cheers,
>   Tammo
>
> --
> Tammo van Lessen - [EMAIL PROTECTED] - http://www.taval.de
>