--- On Tue, 7/29/08, David E Jones <[EMAIL PROTECTED]> wrote:
> From: David E Jones <[EMAIL PROTECTED]>
> Subject: Re: Some Final Ideas/Questions About Fixed Asset Maintenance
> To: [email protected]
> Date: Tuesday, July 29, 2008, 6:40 PM
> On Jul 29, 2008, at 11:48 AM, Adrian Crum wrote:
>
> > My work on Fixed Asset Maintenance and the Asset
> Maintenance
> > component is nearly complete. I have a few remaining
> questions and
> > ideas.
> >
> > 1. The trunk includes the new Asset Maintenance
> feature that
> > automatically assigns parties to the Fixed Asset
> Maintenance Work
> > Effort. If a party is related to the Fixed Asset in
> one of the
> > maintenance roles, then they are automatically
> assigned to the work
> > effort when a new maintenance is created. Should I
> move this feature
> > to Accounting->Fixed Assets?
>
> Are you saying that this is in WorkEffort now or something?
> If that is
> what you mean then I'd say it should be in the
> accounting component
> because in this case the FixedAsset stuff is using the
> WorkEffort
> stuff so FixedAsset is higher level than WorkEffort meaning
> that
> FixedAsset needs to know about WorkEffort, but WorkEffort
> doesn't need
> to know about FixedAsset. So, it should go in the
> FixedAsset area.
No, I was saying that I added the feature to the Asset Maintenance component,
not WorkEffort.
Thanks for the replies on the other issues!
-Adrian