On Sep 17, 2008, at 4:02 PM, Adrian Crum wrote:
David E Jones wrote:
On Sep 17, 2008, at 2:15 PM, Adrian Crum wrote:
What about an employee work schedule? I want to assign an employee
to work in the roof department from 8am to 5pm, Monday through
Friday, with a lunch break from 12:00 to 12:30pm. Where would
those recurring events go?
Here's what I wrote in Jira OFBIZ-1956: "To push this further, and
to answer Jacques' question: the WorkEffort entity is already
designed to handle work schedules using the WorkEffortType
"Available" (ID: AVAILABLE)."
Wouldn't that be confusing? When someone is working they are
available? It seems to me someone is available if they are *not*
working.
That's correct, they're not working, they're available for work. In
other words those are times when events (or tasks with scheduling) can
be assigned, or when looking at all tasks assigned and their estimated
times how many days it will take to complete them (and when each will
start, etc).
-David