Absolutely agreeļ¼ Mario Cappellato commented on OFBIZ-1242: -----------------------------------------
The days to ship are very important for purchase orders. The MRP calculates the requiredByDate from routing tasks and adding the Days to ship to calculate the requirementStartDate. I agree to remove the "ship to day" from the MRP algorithm but I propose to add a new field (mrpLeadTimeMillis) into ProductFacility and replace the "ship to day" with this new field in the MRP. Then MRP algorithm will add all the time mrpLeadTimeMillis to the calculated time of every event. I don't think that forcing the proposed date by MRP at now if the date is before of today is a good idea. As is now is better because you have a clear understanding of how late an order is. -- View this message in context: http://ofbiz.135035.n4.nabble.com/jira-Created-OFBIZ-1242-MRP-days-to-ship-and-inventory-event-planned-dates-issues-tp183662p4636350.html Sent from the OFBiz - Dev mailing list archive at Nabble.com.