I'm going to turn this into a vote, just to get the ball rolling a little faster.

The vote in question is to whether we will cut a release and begin the release voting process on Monday, August 20th, 2007 (with the ultimate goal of having a final 1.0.0 release approved by August 31st). Any new bugfixes or features for 1.0.0 would need to be committed by then.

A vote of +1 approves the cutoff date, a vote of -1 indicates that you think we should wait longer.

To start things off: I cast a vote of +1.



On Aug 7, 2007, at 3:17 PM, Patrick Linskey wrote:

Hi,

At the meeting today, we discussed having a deadline for 1.0.0
features. We mentioned the possibility of the 20th of August as such a
deadline, so that Marc could achieve his responsibilities.

Does anyone have any concerns about such a deadline?

-Patrick

--
Patrick Linskey
202 669 5907