Our quarterly report is due by March 6.  I would like to be able to post
the completed draft by end-of day March 1 (Friday) so we can avoid being
reminded that it is missing.

I have made an initial draft, including updating the quoted project
activity stats here.
https://cwiki.apache.org/confluence/pages/viewpage.action?pageId=103091999

I could use some help in coming up with the list of ICLAs submitted...how
was that done for prior reports?

Having looked at previous reports submitted by many other podlings, I feel
that our typical previous report was too detailed.  I propose we try to
make this report shorter by eliding laundry lists of project-specific
technical progress and focusing on the process-level questions that I think
is the main focus of the IPMC and ASF Board for the quarterly reports.