[For status with links to Wiki pages, see blog post: http://wp.osafoundation.org/2005/07/18/osaf-status-overview-july-19/]

Highlights

    * Chandler milestone 0.5.m4 completed, QA approved, released

Design

* Progress: Big virtuality presentation and papers/images. New sidebar icons. Updated recurrence and sidebar specs. Working on triage prototype with Chao. * Plans: Review M5 plans and tasks. continue work on design Wiki pages, start planning for OSCon presentations. More 0.7 planning.

Applications

* Progress: Edit mode shading, bevelling, minical alignment, blocking bug fixes for milestone.
    * Plans: Recurrence UI checkin, scoping/estimation work for milestone 5

Services:

* Progress: Published new version of RFC2518bis proposal. Tickets support in zanshin library. I18n work moving into impl. mode and resolving issues with attribute redirection. * Plans: Ticket support in sharing. Timezone impl. beginning, sharing termination work, recurrence work * Personnel: Lisa OOF (vacation and conference) until Aug 8; Heikki back

Dev platform:

* Progress: Flickr parcel work, repo viewer update, adding items to packs, Item collection branch created and checkins made, UString and BString types in core schema for i18n, performance work planning * Plans: Finish Set work, more PyICU work, help other teams with Item collection integration, parcel and platform proposals (PJE)

QA

* Progress: Tested m4 and approved, followed up on blocker bugs and fixes. CSV data loading script checked in (Olivier) * Plans: More milestone testing, CPIA script enhancement review, more perf and robustness testing

Cosmo/Scooby

* Progress: Support for CalDAV begun with MKCALENDAR, Brendan’s Scooby mockup in SVN
    * Plans: Continue work on parsing iCalendar.
    * Personnel: Mat Eernisse to start Jul 25

Build

* Progress: Released milestone 4 (0.5.04), many wxPython upgrades, SVN & Bonsai integration
    * Plans: libXML2 upgrade, instrumentation framework design, bug work

Community

    * Plans: OSCon Aug 1-5 and planning for Aug CSG meeting

IT

    * Progress: Server survey underway. High number of tickets closed.
* Plans: Finish Cosmo demo server project and IT application development infrastructure work (SVN, development environments)