[
https://issues.apache.org/jira/browse/PIG-1883?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
]
Olga Natkovich updated PIG-1883:
--------------------------------
Fix Version/s: (was: 0.9.0)
> Pig's progress estimation should account for parallel job executions
> --------------------------------------------------------------------
>
> Key: PIG-1883
> URL: https://issues.apache.org/jira/browse/PIG-1883
> Project: Pig
> Issue Type: Improvement
> Reporter: Laukik Chitnis
> Assignee: Laukik Chitnis
>
> Currently, Pig's progress estimation is based on the percentage of jobs
> completed out of the total number of MR jobs. However, since the MR operators
> are arranged in a DAG (and hence more than 1 job might be submitted for
> execution in parallel), the progress estimation can be improved by
> considering the number of jobs in the critical path, instead of just the
> total number of jobs.
--
This message is automatically generated by JIRA.
For more information on JIRA, see: http://www.atlassian.com/software/jira