We have the next LTS release, Pulsar 4.0, scheduled for October. 
For LTS, releases, our release policy states a 3 week recycle [1].

Suggested timeline:
2024-08-09 - Create & merge PR to bump master branch's version to 4.0.0-SNAPSHOT
2024-09-15 - code freeze for 4.0 by branching branch-4.0 from master branch
2024-09-19 - target release date of 4.0 release candidate 1
2024-09-26 - target release date of 4.0 release candidate 2
2024-10-03 - target release date of 4.0 release candidate 3
2024-10-10 - target release date of 4.0

Unless there's another proposal for the timeline, let's do a lazy consensus 
decision on this timeline in the next 72 hours. We can always adjust this if 
there's a need to do so.

-Lari

1 - https://pulsar.apache.org/contribute/release-policy/#release-cycles