I have updated the report for this quarter at
https://wiki.apache.org/incubator/February2018
See below
========================
Ratis
Ratis is a java implementation for RAFT consensus protocol
Ratis has been incubating since 2017-01-03.
Three most important issues to address in the move towards graduation:
1. Work towards a beta release.
2. Stabilize nightly build process.
3. More committers.
Any issues that the Incubator PMC (IPMC) or ASF Board wish/need to be
aware of?
None
How has the community developed since the last report?
5 new contributors have been added. Total 41 contributors currently.
2 new committers have been elected.
How has the project developed since the last report?
Jenkins setup is completed.
Project website is available at http://ratis.apache.org/
62 new commits to the project. Multiple snapshot releases.
How would you assess the podling's maturity?
Please feel free to add your own commentary.
[ ] Initial setup - Jenkins setup completed. Website available
http://ratis.apache.org/
[ ] Work towards 0.2-alpha has started. Plans for a beta release shaping up.
Need to establish a release cadence.
[ ] Community building - 5 new contributors. 2 new committers.
[ ] Nearing graduation
[ ] Other:
Date of last release:
2017-05-17: 0.1-alpha release
2018-01-23: Last snapshot release
When were the last committers or PPMC members elected?
2018-01-10
=======================================
On 2/1/18, 7:17 PM, "[email protected]" <[email protected]> wrote:
Dear podling,
This email was sent by an automated system on behalf of the Apache
Incubator PMC. It is an initial reminder to give you plenty of time to
prepare your quarterly board report.
The board meeting is scheduled for Wed, 21 February 2018, 10:30 am PDT.
The report for your podling will form a part of the Incubator PMC
report. The Incubator PMC requires your report to be submitted 2 weeks
before the board meeting, to allow sufficient time for review and
submission (Wed, February 07).
Please submit your report with sufficient time to allow the Incubator
PMC, and subsequently board members to review and digest. Again, the
very latest you should submit your report is 2 weeks prior to the board
meeting.
Thanks,
The Apache Incubator PMC
Submitting your Report
----------------------
Your report should contain the following:
* Your project name
* A brief description of your project, which assumes no knowledge of
the project or necessarily of its field
* A list of the three most important issues to address in the move
towards graduation.
* Any issues that the Incubator PMC or ASF Board might wish/need to be
aware of
* How has the community developed since the last report
* How has the project developed since the last report.
* How does the podling rate their own maturity.
This should be appended to the Incubator Wiki page at:
https://wiki.apache.org/incubator/February2018
Note: This is manually populated. You may need to wait a little before
this page is created from a template.
Mentors
-------
Mentors should review reports for their project(s) and sign them off on
the Incubator wiki page. Signing off reports shows that you are
following the project - projects that are not signed may raise alarms
for the Incubator PMC.
Incubator PMC