I strongly believe in time-based goals as being good to keep the project moving forward. I also believe that 3.3.0 that we have now is of very high quality, certainly far more than 3.2.5.

For this reason I want to cut a new pre-release of whatever is in trunk on December 17th. If all P1 bugs targeting 3.3.0 are closed on that date then it will be called 3.3.0-rc1. If there remain P1 bugs then this upcoming pre-release will be called beta2 instead.

Please look at all the 3.3.0 targeted bugs and promote any to P1 that you believe MUST be fixed before 3.3.0 final.

December 17th might seem too aggressive, but looking at the 3.3.0 targeted bugs there really doesn't appear to be much important remaining. If more time is needed then I'm fine with one additional week, cutting around December 23rd instead.

Warren Togami