ok, thanks, Shane!

Bests,
Takeshi

On Sat, Oct 26, 2019 at 7:01 AM Shane Knapp <skn...@berkeley.edu> wrote:

> > 2) the OTHER thing is that PG&E will be potentially cutting power to
> > campus again tomorrow evening and over the weekend.  i am unsure 1) if
> > this is happening, and 2) if our campus colo will go on to generator
> > backup power.
> >
> > if the colo does go on backup power, all of the workers will shut down
> > and power back on automatically when power is restored.
> >
> ok, it looks like the colo will have power until monday morning, and
> it will be shut down from 8am to noon to perform some maintenance.
>
> this means jenkins will be up all weekend, but down monday morning.
>
> shane
> --
> Shane Knapp
> UC Berkeley EECS Research / RISELab Staff Technical Lead
> https://rise.cs.berkeley.edu
>
> ---------------------------------------------------------------------
> To unsubscribe e-mail: dev-unsubscr...@spark.apache.org
>
>

-- 
---
Takeshi Yamamuro

Reply via email to