Robert Joseph Evans created STORM-898:
-----------------------------------------

             Summary: Add priorities and per user resource guarantees to 
Resource Aware Scheduler
                 Key: STORM-898
                 URL: https://issues.apache.org/jira/browse/STORM-898
             Project: Apache Storm
          Issue Type: New Feature
            Reporter: Robert Joseph Evans


In a multi-tenant environment we would like to be able to give individual users 
a guarantee of how much CPU/Memory/Network they will be able to use in a 
cluster.  We would also like to know which topologies a user feels are the most 
important to keep running if there are not enough resources to run all of their 
topologies.

Each user should be able to specify if their topology is production, staging, 
or development. Within each of those categories a user should be able to give a 
topology a priority, 0 to 10 with 10 being the highest priority (or something 
like this).

If there are not enough resources on a cluster to run a topology assume this 
topology is running using resources and find the user that is most over their 
guaranteed resources.  Shoot the lowest priority topology for that user, and 
repeat until, this topology is able to run, or this topology would be the one 
shot.   Ideally we don't actually shoot anything until we know that we would 
have made enough room.

If the cluster is over-subscribed and everyone is under their guarantee, and 
this topology would not put the user over their guarantee.  Shoot the lowest 
priority topology in this workers resource pool until there is enough room to 
run the topology or this topology is the one that would be shot.  We might also 
want to think about what to do if we are going to shoot a production topology 
in an oversubscribed case, and perhaps we can shoot a non-production topology 
instead even if the other user is not over their guarantee.



--