> -----Original Message-----
> From: Julian Foad [mailto:[email protected]]
> Sent: donderdag 19 februari 2015 13:18
> To: [email protected]
> Subject: Issue sweep
> 
> We have the following open issues that have a target milestone set.
> 
>   1.6.x          1 (1 defect)   REVIEW
> 
>   1.7.x          4 (4 defect)   REVIEW
>   1.7-consider  23 (13 defect)
> 
>   1.8.1          2 (2 defect)   REVIEW
>   1.8.x          1 (1 defect)   REVIEW
>   1.8-consider  24 (22 defect)
> 
>   1.9.0          1 (1 defect)
>   1.9.x          0
>   1.9-consider  52 (1 defect)
> 
>   1.10-consider 11 (7 defect)
> 
> I suggest we should:
> 
>   * Review each of the eight issues marked 'REVIEW' above to see if the
> milestone still should be set to a specific old release series. If not,
change it to
> 'unscheduled'.
> 
>   * Bulk reassign every 1.[789]-consider issue to 'unscheduled'. If we
didn't fix it
> for 1.7 or 1.8 or 1.9 there is no particular reason why we should
> *automatically* prioritize it over any other unscheduled issue for the
1.10
> development period.

Usually we would bump 1.X-consider to 1.(X+1) consider instead of the big
unscheduled...

Can somebody with more privileges on Tigris create the right targets?

        Bert


Reply via email to