Nathan Hartman wrote:
    + A change needs three +1 votes (for an LTS release line) or one +1
    vote
    (for a non-LTS release line) from full committers (or partial
    committers
    for the involved areas), and no vetoes, to go into A.B.x.

snip

    - (If a change affects the build system, however, it is considered a
    core change, and needs three +1's.)
    + (If a change affects the build system, however, it is considered a
    core change, and so for an LTS release line needs three +1's.)


Just proofreading...

Is this 2nd change correct or was the intention three +1s for build system changes regardless if LTS or not?

It's correct...

I'm asking because the 1st change already says that changes to LTS require three +1s.

I quoted it here out of its context. In its context it makes sense.

- Julian