All,

I wanted to provide a progress update as I expected to be in a position to start tagging the January release by now and I'm not.

Most of the release preparation is done:
- dependencies have been reviewed and updated where necessary
- i18n sync with POEditor is complete
- open bugs have been resolved
- there are a couple of PRs I hoped to merge this time around that will
  have to wait until Feb but there are for enhancements rather than bugs
- The Tomcat Native updates are complete
- The TLS 1.3 configuration updates are complete

The OCSP protocol updates are where the delay is.

I think everything is working for 10.1.x, 11.0.x and 12.0.x although I do want to complete my usual run of the test suites on Windows, Linux and MacOS before tagging and they might expose a bug or two.

The challenge at the moment is 9.0.x and APR. The TestOscpEnabled test case is seeing a LOT of failures and I don't understand why at this point. It is getting late here so I probably need to start fresh tomorrow. Most of the issues seem to be around the client verifying the server certificate which is really odd since that code should be the same regardless of Connector.

I'm expecting the CI builds for 9.0.x to continue to fail for now but hopefully 11.0.x will continue to pass and 10.1.x will start passing on the next run.

I've seen quite a Native few crashes over that last few days. Nothing obviously repeatable at this point but as the test failures get fixed we might start to see a pattern. We'll see.

Hopefully, there will some progress tomorrow and we'll be in a position to start tagging.

If anyone does have some time available to look at the failing OCSP tests with 9.0.x and APR that would be great but please don't feel you have to.

Mark

---------------------------------------------------------------------