On 02/10/2013 19:15, Bob DeRemer wrote:
> 
> 
>> -----Original Message-----
>> From: Mark Thomas [mailto:ma...@apache.org]
>> Sent: Wednesday, October 02, 2013 1:28 PM
>> To: Tomcat Developers List
>> Subject: Re: 8.0.x / 7.0.x progress
>>
>> On 01/10/2013 19:39, Mark Thomas wrote:
>>> 8.0.x trunk appears to be stable (i.e. no longer crashes)
>>
>> So far no-one has come forward with results to contradict this and folks that
>> reported issues with RC3 have not been able to repeat them.
>>
>> The additional issues reported with the snake example have been resolved.
>>
>> Currently, the 8.0.x unit tests pass (with tomcat native built from
>> 1.1.x) for BIO, NIO and APR/native.
>>
>>> but the
>>> FormAuthenticator unit tests are very slow (24 minutes). This needs to
>>> be resolved.
>>
>> This has been resolved.
>>
>>> I will port the latest APR changes to 7.0.x shortly.
>>
>> Also done.
>>
>>> A build of the latest 1.1.x tomcat-native code is required to achieve
>>> that stability. The implication is that a 1.1.29 release will be
>>> required before the next 7.0.x release.
>>
>> I'm now certain that a tomcat native 1.1.29 release will be required before 
>> we
>> can roll the next 7.0.x release.
>>
>>> The unit tests have identified a rare failure mode in JULI during
>>> context stop:
>>> http://ci.apache.org/projects/tomcat/tomcat7/logs/1527504/TEST-org.apa
>>> che.catalina.websocket.TestWebSocket.NIO.txt
>>
>> This does not appear to be connector related so it is very unlikely that any
>> tomcat native changes would be required to fix this.
>>
>>> The fairly frequent (5%-10%) failure rate of TestCoyoteOutputStream
>>> still needs to be addressed.
>>
>> This appears to impact all connectors so at this point it is unlikely a 
>> tomcat
>> native change would be required.
>>
>>
>> I think we are at a point where it makes sense to start a tomcat native
>> 1.1.29 release. Mladen?
> 
> Please excuse the possibly naïve question, but what does it mean to "start a 
> native release" - in terms of timeline?  Is this a build/test cycle, or is 
> there more involved?   Just curious what we may be looking at with regard to 
> impact on 7.0 GA.

It should just be a build, test and vote cycle followed by the same for
7.0.x.

If an issue is found then it might take longer.

Mark

---------------------------------------------------------------------
To unsubscribe, e-mail: dev-unsubscr...@tomcat.apache.org
For additional commands, e-mail: dev-h...@tomcat.apache.org

Reply via email to