On Thu, Mar 5, 2009 at 1:19 AM, ant elder <[email protected]> wrote:
>
>
> On Mon, Mar 2, 2009 at 11:18 AM, ant elder <[email protected]> wrote:
>>
>> We've talk about a 6 week release cycle on 2.x and the M1 RC1 was done on
>> Feb 9 so six weeks from then is in 3 weeks on March 23rd. That seems like a
>> fine date to aim for M2 RC1 to me, does it sounds ok for everyone?
>>
>> One of the main things I'd like to get done for M2 is to update the build
>> to use the Maven release plugin (TUSCANY-2813) as has been done for the
>> Tuscany plugin builds, that s going to change the release process quite a
>> bit so I'm happy to be the M2 RM to make sure its working properly but if
>> anyone else who hasn't done it before would like a go that would be great
>> too so just volunteer and i can help out with any problems there may be with
>> getting the new release process running smoothly.
>>
>>    ...ant
>>
>
> No comments so I'll assume this is ok and plan to take an M2 branch around
> the 19th of March (thats 2 weeks from now) and an RC out by the 23rd.
>

We successfully did 2.0 M1 without a branch, while this has the side
effect of caution during the release candidate process, it helps by
avoiding inconsistency when people forget to merge, and avoid merging
in general.

>    ...ant
>
>
>



-- 
Luciano Resende
Apache Tuscany, Apache PhotArk