On Thu, May 14, 2009 at 11:49 AM, ant elder <[email protected]> wrote:
> On Tue, May 5, 2009 at 1:01 PM, Simon Laws <[email protected]> wrote:
>> On Tue, May 5, 2009 at 12:53 PM, ant elder <[email protected]> wrote:
>>> On Mon, Apr 20, 2009 at 8:52 PM, ant elder <[email protected]> wrote:
>>>
>>>>
>>>> The Axis2 1.5 release looks like it could start being voted on this week
>>>> but that often can take some time and then the JMS transport would be
>>>> released separately after that and then we'd need some time to polish a
>>>> Tuscany release including those. So all that would likley take some weeks.
>>>> There are alternatives like trying to port the new JMS transport to our
>>>> existing ws binding, but thats likely a bit more work.
>>>>
>>>
>>> If we're to get a 1.5 release out this month I'm starting to think we
>>> should go with porting the new Axis2 JMS transport to work with the
>>> existing Tuscany WS binding.
>>>
>>> Axis2 still haven't had their release and after that does happen there
>>> would need to be a follow on release of the transports and all that
>>> will have to take at lease a couple of weeks and then we'd need to
>>> pick it up in Tuscany before doing the Tuscany 1.5 release...so all
>>> that would likely push the Tuscany release in to June.
>>>
>>> So unless anyone can see any issues with the approach I'm going to
>>> start looking at bringing the new Axis2 JMS transport into the Tuscany
>>> WS binding. At least that will help us know how hard it is to do and
>>> we can throw it all away if the Axis2 releases do start to happen more
>>> quickly.
>>>
>>>   ...ant
>>>
>>
>> Sounds like the right thing to do given where we are. We also have
>> this WSDL issue that Dave raised that I was going to look at. Is it
>> safe to assume that we wait until these are done before retaking the
>> branch?
>>
>> Simon
>>
>
> I've fixed the soap/jms issue in TUSCANY-2916 now, whats the status of
> the wsdl issue in TUSCANY-2900, is the work around in there enough for
> us to start on the 1.5 release again now?
>
>   ...ant
>

I think it is. But maybe what we could do is run though the tests,
legal etc in 1.x before cutting the branch to give a day or so more
for responses. I intend to give the samples a runt through as soon as
I can get done with some 2.x things I'm working on.

Simon

Reply via email to