We have fixed the remaining issues in the integration tests. Now the
AppServer packs gets started successfully. :) Now, I'm doing smoke
tests on the pack. Shall we release this if the smoke tests passed?

Thanks,
--KasunG

On Thu, Jul 26, 2012 at 7:46 PM, Kasun Gajasinghe <[email protected]> wrote:
> Update:
> Still Bamboo fails because of svn issues. When this happens Bamboo
> can't take a fresh checkout, so the whole build fails. I have sent few
> about those.
>
> I'm building AppServer branch locally. I was able to come up to
> platform. Still building the appserver. Got one integration test
> failures. Trying to figure whether it's local to my build.
>
> Thanks,
> --KasunG
>
> On Thu, Jul 26, 2012 at 5:07 PM, Sagara Gunathunga <[email protected]> wrote:
>> We got indication from DS team that they will resolve all L1 within today.
>> Still we have few deployment synchronization issues specially CARBON-13662.
>> As per my chat with  NuwanD still no proper solution for CARBON-13662.
>>
>> We still trying to have RC1 today, from this morning KasunG trying to fix
>> Bambo build issues before the release. The idea is release RC1 today and
>> identify possible new issues before the weekend so that we can reach to 3rd
>> of August deadline safely.
>>
>> Thanks !
>>
>> On Thu, Jul 26, 2012 at 4:51 PM, Samisa Abeysinghe <[email protected]> wrote:
>>>
>>> Are we ready with AS RCs?
>>>
>>>
>>> On Mon, Jul 23, 2012 at 7:05 PM, Anjana Fernando <[email protected]> wrote:
>>>>
>>>> Hi Isuru,
>>>>
>>>> On Mon, Jul 23, 2012 at 2:34 PM, Isuru Suriarachchi <[email protected]>
>>>> wrote:
>>>>>
>>>>> Hi Nuwan/Anjana,
>>>>>
>>>>> As you know, we are trying to ship AS with Carbon core at least by the
>>>>> end of next week and we are targeting an RC from the new branch by
>>>>> Wednesday. So we'll have to fix all L1's and L2's related to MS, Jaggery 
>>>>> and
>>>>> DS components by Wednesday and freez the code. Is that possible? Please 
>>>>> let
>>>>> us know if there are any concerns..
>>>>
>>>>
>>>> For DSS, we have around 15 L1 + L2 issues, so I'm afraid Wednesday may
>>>> not be enough to resolve all of them and code freeze. So how about if we
>>>> code freeze by Friday and do an RC next Monday? ..
>>>>
>>>> Cheers,
>>>> Anjana.
>>>>
>>>>>
>>>>>
>>>>> Thanks,
>>>>> ~Isuru
>>>>>
>>>>> --
>>>>> Isuru Suriarachchi
>>>>> Senior Technical Lead
>>>>> WSO2 Inc. http://wso2.com
>>>>> email : [email protected]
>>>>> blog : http://isurues.wordpress.com/
>>>>>
>>>>> lean . enterprise . middleware
>>>>>
>>>>
>>>>
>>>>
>>>> --
>>>> Anjana Fernando
>>>> Associate Technical Lead
>>>> WSO2 Inc. | http://wso2.com
>>>> lean . enterprise . middleware
>>>>
>>> Thanks,
>>> Samisa...
>>>
>>> Samisa Abeysinghe
>>> VP Engineering
>>> WSO2 Inc.
>>> http://wso2.com
>>> http://wso2.org
>>>
>>>
>>
>>
>>
>> --
>> Sagara Gunathunga
>>
>> Technical Lead; WSO2, Inc.;  http://wso2.com
>> V.P Apache Web Services ;  http://ws.apache.org/
>> Blog ;  http://ssagara.blogspot.com
>>
>
>
>
> --
> Kasun Gajasinghe
> Software Engineer;
> Development Technologies Team, WSO2 Inc.; http://wso2.com ,
> email: kasung AT spamfree wso2.com cell: +94 (77) 678-0813
> linked-in: http://lk.linkedin.com/in/gajasinghe
> blog: http://blog.kasunbg.org
> twitter: http://twitter.com/kasunbg



-- 
Kasun Gajasinghe
Software Engineer;
Development Technologies Team, WSO2 Inc.; http://wso2.com ,
email: kasung AT spamfree wso2.com cell: +94 (77) 678-0813
linked-in: http://lk.linkedin.com/in/gajasinghe
blog: http://blog.kasunbg.org
twitter: http://twitter.com/kasunbg
_______________________________________________
Dev mailing list
[email protected]
http://wso2.org/cgi-bin/mailman/listinfo/dev

Reply via email to