This can be done in a single process.

Start Event -> Service Task ( Update Database) -> User Task ( to Change the
status ) -> Service Task ( to Change the status ) -> End Event.

Thanks,
Hasitha.

On Mon, Mar 28, 2016 at 11:30 AM, Amalka Subasinghe <ama...@wso2.com> wrote:

> Hi,
>
> I have a scenario like
> 1. User log in and fill a form and save, it will save in external database
> with the status 'Created'
> 2. later time User log in again, he sees the records which are in
> "Created" status and change the status of those records to 'In Progress',
> it will again update the database.
>
> for this kind of scenario, the best approach would be creating 1 BPMN
> process including both or creating 2 BPMN processes ?
>
> Thanks
> Amalka
>
>


-- 
--
Hasitha Aravinda,
Senior Software Engineer,
WSO2 Inc.
Email: hasi...@wso2.com
Mobile : +94 718 210 200
_______________________________________________
Dev mailing list
Dev@wso2.org
http://wso2.org/cgi-bin/mailman/listinfo/dev

Reply via email to