Hello Everyone,

Below are the meeting minutes from our weekly status meeting on Wed May 25, 
2016.

Tasks completed:
1. Deployed WSO2MB product using puppet provisioning. 
2. Completed code walk though of puppet-modules with understanding of Hiera and 
related dependencies.
3. Pull request to fail fast if docker daemon is not running has been merged.

Next steps:
1. Develop concrete milestone plan for test framework with focus on tasks to be 
completed within mid-term evaluation.
2. Utilize the current bash test script from Chamila as a basis for writing 
tests.