Software Meeting 11/28/2006

Attending:

Richard Smith
Lillian Walter
Jordan Crouse
John Palmieri
Mitch Bradley
Ted + Victor from Quanta
Marcelo Tosatti
Ivan and Chris Ball

Mitch running the meeting
Chris taking notes

Action Items:

AI: Victor will talk to Mark about quantity for Beta 2
AI: Blizzard to see where Beta 2 units are going (developers, countries)
AI: Mitch to own power project for Beta 2
AI: Chris Ball to own performance
AI: Chris Blizzard to own stability
AI: BIOS team to deliver working BIOS bits tomorrow (nov 29)
AI: John Palmieri to work on image updater with new BIOS (nov 29)
AI: Blizzard to find out from Lindsay how many we're sending out
AI: Jordan to work on getting DCON and X hacks out and get real fixes in now that Beta 1 is done
AI: Blizzard to talk to Andres about new kernel feature (.19)
AI: Victor to tell Mitch what chips they are using and send samples to Mitch for ethernet on the line
AI: Lots of bug triage for everyone

o Schedule for B2
- Integrated Verification Test by Jan 15 minus a week for Christmas vacation

o Should use trac for btest-2

o What outstanding items will we have by beta2?
- Victor: Mark says 500 units for beta2
- Victor will discuss with Mark next week to double check
- Not sure that they will have units to us by jan 15th, that's when the quanta testing team gets first units
- Those units will go where?
  - No distribution list yet - not sure where they are going to go
  - Chris: guessing some refreshes for developers, but mostly for countries

o Power Management for beta2 - want to have something to demo
o Performance, stability and power management - focus points for the next 6 weeks
o Beta2 builds will get faster python, which means faster sugar
o But with half the memory
- Python 2.5 has better memory management, if we go that route

o Preview of document stuff in place by beta2?
- Should have a working eBook reader by the end of this week? John is coming into the office and has a working reader. Will require 2-5 of integration work before it's ready to be put into the build.

o ROM security is not a priority for the next build, should target at beta3
  - Prototyping as available, but not pushing for beta2
- Should have crypto bits for the bios by Nov 30th (code to see if an image is properly signed.) - Last bit is EC changes to clear the write protect bits? Not tested, but Mitch thinks it is in.

o Blessed software bits?
- Richard has built what is supposed to be the right stuff, still has the brick. Waiting on that.
- Software?  Any testing time on 187?
  - Haven't done any testing on that yet.
  - Chris Ball has a keyboard problem of some kind?
  - John thinks it's fine and is running it on his box.
- It checks for a-test it doesn't load the module and uses a different xorg.conf. - Only differences between 185 + 187 is the module loading and the xorg.conf
  - What other testing do we need to do?
- Load them on a few more machines and make sure that the i80* driver is loaded and the right xorg.conf is copied over. - Need to do some functional testing + tinderboxing + boot it on an a-test - Make sure it works with the new buildrom update and make sure that it leaves the manufacturing data is intact
    - at the OK prompt and there's a one line check for it

- Also need to generate an auto-update image that flashes the BIOS and push the right build onto the nand
  - Doesn't have to be the same build
  - Might need a > 1G key - can use the little seagate drives
- John has done it in the past with a manual step, but we can hook that up to an init script
  - Get a minimum build with a 512 key if we want
  - Want to make sure
  - Need to talk to lindsay about how many go out tomorrow
  - Maybe pull olpcflash out of the build?  Maybe not
- Blizzard won't be in the office, John volunteers to sign up to run this process WE HAVE A WINNER!

o Ramping back up?
- Get update stuff out of the way and then get serious about power management - Mitch will drive that once we're done
- Chris will be driving Performance goals
  - Baselines for performance need to be established
  - Track progress - Chris will be driving some of that with new tbox stuff
- Stability - Chris Blizzard will own
  - Hard to measure
  - Memory Management (also can measure)
  - Process-wise making sure that things don't break over time
  - Smoketesting Procedures - running through a set of tests
  - Over time testing - 100 most popular pages and see how long we last
  - Need to automate sugar somehow
- Milestones for progress for build time and when we will do feature freezes

o Cleanup from btest1
- Unscrew A-test
  - Need to work on an updated a-test image at some point
  - Not in bad shape
- Wireless on A-test?
  - Wireless was having problems (from Richard?)
  - Needs more investigation
  - don't know what boot firmware was on it, need to investigate
  - Richard will test
- Cleaning up a bunch of apps
- X needs to be fixed
  - Lots of fixes for btest-1 that need to get cleaned up post-btest
  - Some DCON fixes as well

o Major pieces to include
- New kernel? (2.6.19?)
  - Job for Andres!
- New Python (2.5?)
- Let's document in trac or spreadsheet
- AI: Blizzard to talk to Andres for new kernel, etc

o Network support for manufacturing?
- High priority for beta test 2?
  - Would be good to test for beta2
  - What about the slow ethernet?
    - AI: Victor will tell Mitch the chips that they use
    - AI: Victor needs to send specific parts to Mitch for building/testing

o Ivan: looking at trac we have a number of bugs that are still targetted at old test builds
- Need to make sure that they are retargetted or closed at some point

o Bug triage

27: stress tester: cjb did an image for this and gave it to tests at quanta
  - Will close and will continue to enhance the testing
  - Quanta does have manufacturing testing and their own procedures
  - AI: Ivan: Will close with a comment that it was delivered to Quanta

43: wireless mesh software: we do have this and there's driver support
  - AI: blizzard: need to add a comment that it needs testing

270: USB high speed issues: engineers are still looking at those on pre-b boards
  - AI: David Woodhouse: See if the problems still exist on btest2
  - AI: Chris will retarget a btest2

272: 273: 274: 275: all same problem, chris will retarget at btest2
  - 273 should be reassigned to jordan

280: delay in dcon -> gpu transition: hasn't been touched since nov 6
  - Have a fix at amd but didn't want to add right before
- AI: Jordan will check with David Woodhouse to see if we need to get the right fix into the right place - Will affect power management as well, need check (turning off panel earlier rather than later)

298: Wireless device appears + disappears: from comments mfoster believes this is a problem with the known power issues in beta1?
  - AI: need to ask david woodhouse and retarget at beta2

409: high number buttons as primary: owned by warp: jg says this is solved by new evdev that's in 172 needs testing by someone before closing
  - Needs testing: AI: retarget to beta2 and need to verify fix

454: wireless oops: dan williams:
  - AI: change owner to marcelo and change to beta2

455: OF failed to set device address: 1: new firmware might solve this, but solve this - AI: Chris will retarget to beta2 and ask marcelo to test with hardware and new firmware

331: sort out keymap: getting keymaps into X
  - Keymaps should all be in, need to be tested on the actual keyboards
  - AI: retarget to beta2 and add a comment to test this

461: overwriting manfacturing data
  - fixed in new image
  - olpcflash will be fixed after we get the update image out the door
  - move to beta2

213: hacking the kernel
  - beta2, move to andres

420-424 for various keymaps
  - Close these for 331 - we do have all the keyboards

512: beta test 1b auto update image
  - Should be done by tomorrow

446: sugar keys not working
  - retarget for beta2 with comment about only camera not working

476: manfacturing data values are in wrong order
  - Close it, it's fixed