The parameter "Locked" on the Setup tab of the production order will not reschedule the production order. I think your are looking for that.
HK
baumgartner_helbling <[EMAIL PROTECTED]> wrote:
Hi all
If i have a production order which is in the status "started" (no
picking of material and no route jobs) and has a assigned end-date,
i don't want the masterplan to calculate a new end-date. Because i
know that i will finish the production in time at my original end-
date.
I alway thought, that the parameter "blocked" on the production
order will exactly do that. But unfortunately it doesn't.
Does anyody knows a solution for this?
Kind regards
Michael
PS. I'm running Axapta Ver. 3.0 Sp2
Yahoo! Groups SponsorADVERTISEMENT
---------------------------------
Yahoo! Groups Links
To visit your group on the web, go to:
http://groups.yahoo.com/group/development-axapta/
To unsubscribe from this group, send an email to:
[EMAIL PROTECTED]
Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.
---------------------------------
Do you Yahoo!?
New and Improved Yahoo! Mail - 100MB free storage!
[Non-text portions of this message have been removed]
| Yahoo! Groups Sponsor | |
|
|
Yahoo! Groups Links
- To visit your group on the web, go to:
http://groups.yahoo.com/group/development-axapta/
- To unsubscribe from this group, send an email to:
[EMAIL PROTECTED]
- Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.