Hello all
Can anybody help me with the following problem:
I have a production order in the status scheduled (operation
schedule). And i have for the same item a planned production order.
When looking at the capacity reservation of a certain ressource i can
see for the dynamic plan both - the production order and the planned
production order. But for the static plan i only see the planned
production order - also if i execute the static plan. In fact i never
see in the static plan any production orders.
This makes absolute no sense for me, because the static plan should
contain the whole situation while the dynamic plan should show the
changes.
I'm really wondering if someone could give me a hint.
Kind regards
Michael