Hi,
Sorry. I am on the travelling for my lab work, and the network here is
invalid. Now I am using my cell phone to check mails. I will back in a
week.
I think the roadmap is OK. I will make a schedule for this when I am back.
I have one problem for this, I am hunting for a job as I am in my last
year in school. What's more, the work in lab is busy. So I do not have
grant time to do the project. But I will try. I think I can finish the
project when 1.7M2.
WDYT?
Thanks.
On 9/21/08, Vincent Massol <[EMAIL PROTECTED]> wrote:
> Hi Wang,
>
> Long time no hear, you must be busy :)
>
> Could you let us know what's the status WRT to cleaning up the office-
> generated HTML?
>
> The roadmap I'd like to have is to have it fully working for 1.7 final
> (that's for the 1st of December). Do you think that's feasible?
>
> My take is that we should have some pretty solid cleaning up by 1.7M1
> if we want to have a chance of it being finished for 1.7 final.
>
> Here's the currently planned 1.7 dates:
>
> - 1.7M1: 20th of October (that's more than 3 weeks after the 1.6
> release)
> - 1.7M2: 10th of November (3 weeks after 1.7M1)
> - 1.7RC1: 17 Nov (one week after)
> - 1.7RC2 or final: 24 Nov (one week after)
> - 1.7 final (if needed): 1st of December
>
> WDYT? Do you need any help to achieve this?
>
> Thanks
> -Vincent
>


-- 