Hi, Following our roadmap definition (now on http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) here are some date proposals for XE 2.1:
* 2.1 M1: 26 Oct (that's 4 weeks after the 2.0 release) * 2.1 M2: 16 Nov * 2.1 RC1: 30 Nov * 2.1 Final: 7 Dec Here's my +1 to commit to this schedule. Note that I propose a not too long release (2 months and 2 weeks) since 2.1 is meant to be a stabilization release with not many new things. The new things should be for 2.2 in 2010. Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs